NHBC Standards 2006

8.2 Wall and ceiling finishes

Appendix 8.2-A
   Dry lining to receive ceramic wall tiling

Appendix 8.2-A

Dry lining to receive ceramic wall tiling

Dry lining to receive ceramic wall tiling
DescriptionBoard thickness
mm

Support centres
mm
Additional supportMax. height
mm
Comments
Timber frame12.5, 15
400 to 450

600
No

Timber noggings 600 mm centres vertically
3600

3600

Timber battens12.5, 15
400Battens at head, base and intermediate positions not exceeding 1200 mm centres3600
Direct bond9.5
450
dabs of adhesive in rows
Horizontal dabs at mid-storey height3600Complete at least
10 days before tiling
Direct bond
(Thermal laminates)
12.5, 15
600
dabs of adhesive in rows
Horizontal dabs at mid-storey height3600Complete at least
10 days before tiling
Metal furring12.5, 15
400
metal furring sections
Metal furring stops at head, base and intermediate positions not exceeding 1200 mm centres3600Complete at least
10 days before tiling
Resin base adhesive
(Thermal laminates)
All
Blob of sealant9 nailable plugs per board

Independent steel stud lining

48 mm

60 mm



2 x 12.5

2 x 12.5




400





Mid-point support

Mid-point support



3000

3600

48 mm metal stud partitions





70 mm metal stud partitions





146 mm metal stud partitions
15

2 x 12.5 each side
2 x 15 each side

15

2 x 12.5 each side
2 x 15 each side

2 x 15 each
side

400

400




400

400




600














Additional stud at 300 mm up to tile height
2700

3600
3600



3600

3600
3600



3600

Prefabricated gypsum wallboard panel partition57
63
}Normal specification
2700
Laminated partition50
65 
}Normal specification
2600
2800
Complete at least 10 days before tiling