NHBC Standards 2011

4.5 Raft, pile, pier and beam foundations

SCOPE

This Chapter gives guidance on meeting the Technical Requirements and recommendations for raft, pile, pier and beam foundations.

DESIGN STANDARDS

4.5 - D1 Design standards
4.5 - D2-D3 Statutory requirements and other standards
4.5 - D4 Hazardous ground
4.5 - D5 Notification
4.5 - D6 Supervision by an Engineer
4.5 - D7 Requirement for foundations
4.5 - D8 Site conditions
4.5 - D9 Differential settlement
4.5 - D10 Services, including drainage
4.5 - D11 Movement joints
4.5 - D12 Damp-proofing
4.5 - D13 Safe transmission of loads
4.5 - D14-D15 Provision of information

4.5 - D1
Design shall meet the Technical Requirements
 

Design that follows the guidance below will be acceptable for raft, pile, pier and beam foundations.

STATUTORY REQUIREMENTS AND OTHER STANDARDS

4.5 - D2
Design shall comply with statutory requirements
 

Design should be in accordance with relevant Building Regulations and other statutory requirements.

4.5 - D3
Design shall follow relevant Standards and Codes of Practice
 

Relevant British Standards and Codes of Practice include:

BS 648 Schedule of weights of building materials
BS EN 1991 Actions on structures
BS EN 1992 Design of concrete structures
BS EN 1997-1 Geotechnical design:General rules
BS 10175 Investigation of potentially contaminated sites - Code of practice.
 

HAZARDOUS GROUND

4.5 - D4
The design of foundations shall take account of the characteristics of the site, its ground and any hazards
 

Where there is hazardous ground, the foundation design must be carried out by an Engineer in accordance with Technical Requirement R5.

Details of ground hazards to be taken into consideration are given in Chapters:

4.1 'Land quality - managing ground conditions'

4.2 'Building near trees'

NOTIFICATION

4.5 - D5
NHBC shall be notified before work starts on site
 

NHBC Rules state:
"If a Home is to be constructed on a Hazardous Site you must before making an Application for Inspection notify the NHBC in writing of the particular hazards which arise. You must do this at least 8 weeks before work begins on the site."

SUPERVISION BY AN ENGINEER

4.5 - D6
When foundations have been designed by an Engineer, the Builder shall require the Engineer to visit the site during construction
 

The visits by the Engineer are necessary so that the Engineer can be satisfied that the design of the foundation is suitable for the actual ground conditions encountered and that the construction is in accordance with the design.

REQUIREMENT FOR FOUNDATIONS

4.5 - D7
All masonry and all loadbearing elements shall be adequately supported by foundations
 

Elements requiring foundations include the following:

  • external walls
  • separating (party) walls
  • chimney breasts
  • piers
  • internal loadbearing or masonry walls
  • sleeper walls.

SITE CONDITIONS

4.5 - D8
Foundations shall be designed to suit site conditions
 

Items to be taken into account include:

(a) site and ground appraisals

All information relating to the site and its ground conditions which is necessary for full and proper foundation design should be obtained.

(b) dwelling design

Foundation design should take account of the shape, size and construction of the dwellings as well as the site layout.

Foundations for terraced dwellings may require special precautions to prevent damage from differential settlement.

(c) site layout

Building over changes in ground characteristics should be avoided.

(d) site levels

Stepped foundations and suspended floor slabs may be needed for sloping sites.

 

(e) sulfate and acids in ground or groundwater

Sulfates and other chemicals can cause expansion and disruption of concrete. Also, high acidity, for example in peat, or permeable soil with acidic groundwater, can cause damage to concrete. Where concrete is at risk from chemical attack from the ground or where the groundwater is highly mobile, the level of sulfate and other chemicals should be determined, in terms of the ACEC Class (Aggressive Chemical Environment for Concrete Class) in accordance with BRE Special Digest 1. Where sulfates or high acidity in ground or groundwater are present, reference should be made to Chapter 2.1 'Concrete and its reinforcement' (each section) for guidance concerning acceptable concrete mixes.

(f) trees

Where trees are nearby or are to be planted nearby (especially where the soil is shrinkable), foundations should be designed as shown in Chapter 4.2 'Building near trees'.

(g) frost susceptible soils

To avoid damage from frost action, the depth to the underside of the foundation in frost susceptible ground should be at least 450mm below finished ground level.

DIFFERENTIAL SETTLEMENT

4.5 - D9
Foundations shall be designed to take account of differential settlement
 

Foundations should be designed to avoid any local stress points or any differential settlement. Foundations for attached bays, porches, garages, conservatories and other structures should be a continuation of those for the main dwelling, unless the design indicates an alternative which takes account of differential movement, for example separate foundations. Foundations adjoining those of an existing building may require special precautions to limit differential movement.

SERVICES, INCLUDING DRAINAGE

4.5 - D10
Foundation design shall take account of access for services
 

Where services are to pass through, or under, foundations provision should be made for suitable ducts or lintels to enable them to be installed later, in such a way as not to impair structural stability. For further details, reference should be made to the Design and Sitework sections of Chapters:
5.1 'Substructure and ground bearing floors'
5.3 'Drainage below ground'
8.1 'Internal services'.

MOVEMENT JOINTS

4.5 - D11
Movement joints should be suitable for their intended purpose
 

Movement joints should be located so as to limit the risk of damage caused by movement. Suitable materials are given in the Materials section.

DAMP-PROOFING

4.5 - D12
The foundation design shall prevent the passage of moisture to the inside of the dwelling
 

Items to be taken into account include:

(a) a drained cavity

Cavity walls should drain below dpc and prevent water flooding cavities above dpc levels or crossing from the outside to the inside. A clear cavity of 225mm minimum below dpc is required. Where foundations other than strip or trench fill are used, including those for timber framed dwellings, this may be reduced to 150mm minimum below dpc provided that weep holes and other measures, where necessary, are taken to ensure that the cavity can drain freely. Dpc cavity trays are not an acceptable weather-proofing to the edges of specialised foundations, such as rafts and ground beams.

Drained cavity ground beam

Drained cavity raft foundation

(b) damp-proof membranes

For the provision of damp-proof membranes, reference should be made to Chapters 5.1 'Substructure and ground bearing floors' (each section) and 5.2 'Suspended ground floors' (each section).

SAFE TRANSMISSION OF LOADS

4.5 - D13
Foundations shall transmit the loads from the structure to the supporting strata safely and without excessive settlement
 

Items to be taken into account include:

(a)
need for adequate stiffness to ensure differential movement does not adversely affect the supported structure
 
(b)
the nature and bearing capacity of the fill material to be placed under the foundation
 
(c)
specification of concrete
 
(d)
cover to reinforcement
 


RAFT FOUNDATIONS

Rafts and semi-rafts should:

  • meet Clauses D1 to D12, where applicable
  • prevent the erosion of ground beneath the raft
  • be designed to accommodate, where required, warm air ducts, service ducts or services without any adverse effect upon performance of the foundation.

Where appropriate, precautions should be taken to limit the risk of ducts becoming flooded.

Semi-raft foundations on made ground should follow the guidance given in Appendix 4.5-A.

For details of suitable fill for raft foundations, refer to Chapter 5.1 'Substructure and ground bearing floors' Appendix 5.1-A.

PILED FOUNDATIONS

Piled foundations should:

The design should specify precautions to be taken in cohesive soils where volume changes can occur.

The bearing capacity and integrity of piles should be confirmed by testing, when required.

PIER/PAD AND BEAM FOUNDATIONS

Pier/pad and beam foundations should:

  • meet Clauses D1 to D12, where applicable.

VIBRATORY GROUND IMPROVEMENT TECHNIQUES

Vibratory ground improvement should:

PROVISION OF INFORMATION

4.5 - D14
Drawings and specifications should be produced in a clearly understandable format
 

All relevant information needed for the completion of the sitework should be stated clearly and unambiguously and be readily available to all concerned.

All necessary dimensions and levels should be indicated and related to:

  • at least one bench mark, and
  • reference points on site.
4.5 - D15
Designs and specifications, together with relevant site information, shall be distributed to appropriate personnel
 

Details should be provided with respect to:

  • dimensions, type and depth of foundations
  • junctions
  • steps
  • movement and construction joints
  • detailing of ducts
  • location of services
  • critical sequences of construction.

Designers need to be aware of the ground conditions and, in particular, any features requiring special attention, such as any existing sewers or other services, levels of water table and the presence of any deleterious substances, especially sulfates.

Where toxic materials (or materials likely to present a health hazard) are found, all available information should be supplied to NHBC, together with proposals for dealing with the hazard.