NHBC Standards 2006

6.2 External timber framed walls

SITEWORK STANDARDS

6.2 - S1Sitework standards
6.2 - S2Construction
6.2 - S3Breather membranes
6.2 - S4Wall ties
6.2 - S5Insulation
6.2 - S6Vapour control layers
6.2 - S7Cladding
6.2 - S8Control of fire
6.2 - S9Services

6.2 - S1
All sitework shall:
(a) meet the Technical Requirements
(b) take account of the design
(c) follow established good practice and workmanship
 

Sitework that complies with the design and guidance below will be acceptable for external walls of timber framed dwellings, substantially timber framed dwellings and wall panels.

All relevant information in a form suitable for the use of site operatives should be available on site before construction starts including:

  • full set of drawings
  • materials specification
  • fixing schedules
  • nailing details
  • manufacturers' recommendations relating to proprietary items.

CONSTRUCTION

6.2 - S2
Construction shall ensure that the building is structurally adequate
 

Items to be taken into account include:

(a) setting out

The substructure should be correctly set out to receive the timber frame which will be manufactured to close tolerances. The timber frame should be checked to ensure that it is erected accurately both on plan and vertically. The load from the frame should be supported as intended in the design.

12mm maximum overhang of frame over supporting structure

Ledges can form moisture traps. Where these occur protection should be provided.

Frame set back 12mm maximum from edge of supporting structure. Ledge protected by breather membrane

The bed between the frame and substructure should:

  • not be more than 20mm thick
  • be the full width of the frame
  • support each stud
  • be durable
  • not deform under load.
Bed 20mm max

(b) anchoring the frame

The frame should be anchored to resist both lateral movement and uplift. Care should be taken to avoid splitting timber plates.

When shotfiring, care should be taken not to spall edges of masonry or slabs. When shotfiring into masonry, solid concrete blocks with a crushing strength of 7N/mm2 should be used, positioned to receive fixings.

Concrete blocks with a crushing strength of 7N/mm2

Fixing to sole plate

Fixing to studs

(c) fixing panels

All fixings should be as scheduled in the design including nailed joints and sheathing.

Wall panels should be securely fixed together and to floor and roof framing.

In Scotland, sole plates and head binder plates should be provided to bind the panels together where there are joints between wall panels. Joints in sole plates and head binder plates should not coincide with those of the panels.

In England, Wales, Northern Ireland and the Isle of Man, joists and roof trusses should bear directly over studs if head plates are not provided.

Individual studs should be not less than 37mm wide, at maximum 600mm centres, unless other adequate support is provided for wall boards and fixings and agreed by NHBC.

A lintel and cripple studs should be provided to any opening in loadbearing panels except when the opening does not affect the stud spacing or where the supported loads are redistributed by a perimeter joist.

Unless otherwise clearly specified by the designer, multiple studs should be included to support multiple joists.

Narrow, inaccessible gaps between studs which are difficult to insulate should be avoided.

(d) supporting claddings

Masonry cladding should not be supported on timber.

Wall ties should be flexible and fixed to studs.

Battens supporting lightweight cladding should be fixed to studs.

(e) fixing plasterboard

Plasterboard should be fixed in accordance with Chapter 8.2 'Wall and ceiling finishes' (Sitework).

Particular care should be taken at the junction between walls and roofs. Reference should be made to Chapter 8.2 'Wall and ceiling finishes' (Sitework).

(f) movement between timber frame wall and other elements

BALLOON CONSTRUCTION

In balloon construction, dwelling height studs are used to which the floor is attached. This form of construction is not commonly used in the United Kingdom. The timber frame designer's recommendations for differential movement allowances should be followed.

PLATFORM CONSTRUCTION

This is the use of storey height panels separated by floor joists.

When using this form of construction either the designer's recommendations should be followed or the following allowances used to accommodate differential movement:

LocationSuspended timber ground floor when panels are supported on ground floor joists or perimeter joistsOther groundfloor construction
Ground floor openings5mm3mm
First floor openings12mm9mm
Second floor openings18mm15mm
Eaves and vergesAdd 3mm to the allowance for openings on that floor

For timber framed buildings more than three storeys high allowances should be extrapolated from the table by 6mm for each additional storey.

The design should be checked to see how the differential movement is allowed for at openings.

At eaves and verges a gap should be left above the masonry which can close as the timber shrinks. Sealing the gap is not required if it is protected by the eaves overhang.

In buildings of four storeys or more it is important that the wall ties are capable of allowing for the likely differential movement.

Do not deviate from those specified.

The design should be checked to see if allowances are made for vertical or horizontal movement in the following locations:

  • the eaves
  • sills of openings
  • heads of openings
  • jambs of openings.

The design should specify the required allowance. If it does not the designer should provide details of the allowances.

An allowance for shrinkage should be made at the eaves.

Allowance for shrinkage

At sills of openings leave a gap sealed with a compressible sealant.

At sills of openings gap should be sealed with compressible sealant

At heads of openings allow for a gap to open. Seal the gap with an expandable sealant or ensure it is well weathered. Do not fix lintels supporting outer leaf masonry rigidly to the timber frame. Allow space between the lintel and its clips for differential movement.

Allow space between lintel and its clips for differential movement

At jambs of openings allow for shear movement between masonry and joinery.

Flexible sealant at point of movement

Where joinery (eg window frames) is fixed to the masonry, the design should be checked as special details may be required.

CLADDING FIXED TO THE FRAME

Allowances are not required around openings or at eaves and verges.

A gap, protected against rain penetration, should be left at horizontal junctions with masonry.

Gap to allow for frame shrinkage

Shear movement should be allowed at vertical junctions with masonry.

Movement joint

CHIMNEYS OR FLUES

A joint should be constructed between chimneys or flues which will prevent any load being transferred onto the chimney or flue.

(g) cavities

A cavity should be provided to reduce the risk of rain penetrating to the frame. The following minimum cavity widths, measured between the claddings and sheathings, should be provided:

CladdingMinimum cavity width
Masonry50mm nominal
Render on unbacked lathing50mm nominal
Render on backed lathing25mm nominal
Vertical tile hanging without underlayNo vertical cavity required when a breather membrane is fitted to the sheathing
Other cladding10mm

The cavity should be extended at least 150mm below dpc, to form drainage to the cavity, and should be kept clear. Weep holes should be provided where necessary to prevent water build up in the cavity.

Deviations in vertical alignment should not exceed 10mm in any storey height.

Minimum width of cavity maintained. Deviation in vertical alignment not more than 10mm

BREATHER MEMBRANES

6.2 - S3
Breather membranes shall where required protect the sheathing from dampness
 

Special attention should be given to the following details:

  • laps, which should be at least 100mm on horizontal joints and 150mm on vertical joints as shown in the following diagram
  • direction of laps, upper layers should be fixed over lower layers to ensure rain runs away from the sheathing. Vertical joints should be staggered wherever possible
  • fixing should be at regular intervals to prevent damage by wind and should be not less than 500mm centres and in accordance with manufacturers' instructions
  • marking the stud positions for wall tie fixing
  • shedding water away from the lowest timber
  • use of self extinguishing grade membrane
  • use of high performance breather membrane in areas of Very Severe exposure (unless the alternatives given in Design Clause D4(c) are adopted)
  • use of fixings described in Chapter 6.2 (Materials).

Damaged membranes should be repaired or replaced.

Damaged membranes

When bitumen impregnated fibre building board is used and a breather membrane is not specified the joints of the boards should be closely butted.

When a breather membrane is not required the bottom frame members should be protected from water running down the cavity.

Bottom frame members should be protected from water running down the cavity

WALL TIES

6.2 - S4
Wall ties shall be correctly installed
 

Wall ties should:

  • be fixed to studs not sheathing
  • slope away from the sheathing towards the cladding
  • be sufficiently flexible to take up differential movement
  • be kept clean and free from mortar droppings.

Wall ties should be spaced as required by the design but not greater than 600mm horizontal and 450mm vertical maximum spacing. At jambs of openings spacing should be a maximum of 300mm vertically with ties set within 300mm of the masonry reveal. In certain locations the design may require closer spacings.

INSULATION

6.2 - S5
Insulation shall be correctly installed
 

Insulation should cover the whole wall area between studs. No gaps should be left:

  • against studs or rails
  • at corners
  • against noggings
  • at junctions with partitions.
Junctions with partitions

Insulation with a backing membrane of any material shall be installed with the backing on the warm side of the insulation.

VAPOUR CONTROL LAYERS

6.2 - S6
Vapour control layers shall be correctly installed
 

Before fixing a vapour control layer the framing timbers should have a moisture content of 20% or less.

The vapour control layer should be fixed on the warm side of the insulation and frame.

The vapour control layer should be formed of the material specified by the design. Minimum 500 gauge polyethylene sheet or vapour control plasterboard should be used. Where vapour control plasterboard is used joints between sheets should be positioned on studs or noggings and the joints should be filled, taped and finished.

Where polyethylene is used all joints in the vapour control layer should have at least 100mm laps and be located on studs or noggings.

Vapour control layers should be fixed at 250mm centres to the top and bottom of the frame, at laps and around openings.

When cutting vapour control plasterboard care should be taken not to displace the vapour control material.

Any holes made in a vapour control layer should be made good and sealed.

The vapour control layer should cover the entire external framed wall area including rails, studs, reveals, lintels and sills.

The vapour control layer should lap with the dpc.

CLADDING

6.2 - S7
Cladding and its fixings shall not obstruct the cavity and shall allow for differential movement
 

Allowance for differential movement between various components should be made as detailed in Clause S2 of this Chapter.

No horizontal batten supporting cladding should be in contact with the sheathing except in the case of tile hanging.

The cavity should be ventilated although it is not necessary to provide through ventilation. Where wall areas are divided by cavity barriers (see Design clause 6.2 - D7) the ventilation openings should be adjacent to barriers at the lower level.

The ventilation openings should be equivalent to open brick perpends every 1.5m.

Ventilation slots should be placed to prevent the ingress of rain or should be below the lowest timber. Weather protected proprietary perpend ventilators are available.

The cavity should be kept clean, free of obstructions and should be capable of draining freely.

All proprietary cladding should be fixed in accordance with manufacturers' instructions.

Masonry cladding should be constructed in accordance with Chapter 6.1 'External masonry walls'.

CONTROL OF FIRE

6.2 - S8
Fire spread shall be controlled as detailed in the design
 

CAVITY BARRIERS

Cavity barriers should be installed in positions detailed by the design and relevant Building Regulations.

Cavity barriers should be formed of materials specified in the design. If no specification is available the advice of the designer should be obtained.

Horizontal cavity barriers (except under eaves) should be protected with a dpc tray. The tray should have a minimum upstand of 100mm. Alternatively polyethylene encased cavity barriers providing a minimum upstand of 100mm should be used.

Breather membrane lapped over dpc tray

Vertical timber cavity barriers should be protected from moisture by a dpc.

Vertical timber cavity barriers should be protected by a dpc

FIRE-STOPPING

Fire-stops should be installed in positions detailed in the design and relevant Building Regulations.

Only those materials specified in the design should be used for fire-stopping.

If details of fire-stop design, location and materials are not available they should be verified with the designer before construction commences.

Fire stops

SERVICES

6.2 - S9
Services shall not reduce the fire resistance or stability of the dwelling
 

Services should not pass through separating wall cavities.

Service outlets should not impair the fire resistance of floors and walls.

In Scotland services are not permitted within a timber framed separating wall cavity.

Notching or holing structural timber members should be carried out as detailed in the design. If these details are not available the designer should be consulted before such operations are started.